Rendering cost in Sydney: eight worked examples

worked quote examples - rendering cost sydney

Ranges are useful, but worked examples make them concrete. Here are eight illustrative rendering jobs priced from the rows in our Sydney table — what the walls are, what system suits them, and the area × the per-square-metre row, with the working shown. They are examples, not collected quotes; the totals are the lines added at the table's typicals.

Eight worked Sydney rendering examples

pricing up a job with notepad and calculator - rendering cost sydney

1. Single-storey brick cottage, cement render and paint

118 m² of sound clay brick, two-coat cement render with a sponge finish, then two coats of exterior paint. No scaffolding (single storey), easy front and rear access. At the typicals in our Sydney table that is 118 m² × $52 cement render = $6,136, plus 118 m² × $23 painting over new render = $2,714 — $8,850 all up (cement render runs $34–$69/m², painting $14–$34/m²). A clean, textbook job — the kind the base rows are built on.

2. Double-storey rendered refresh, acrylic

260 m² across two storeys, existing tired render hacked off in patches and re-rendered, finished in a coloured premium acrylic. At the typicals: 260 m² × $63 acrylic render = $16,380, plus two-storey scaffolding at $2,875 (the table's row is $1,725–$4,600) — $19,255 before the patch removal, which is $17–$46/m² of old render taken off. Height plus a premium finish is what pushes a two-storey job well past a single-storey one.

3. Hebel extension, acrylic system

95 m² of new Hebel panel on a rear extension, flexible acrylic render system (mandatory for the substrate), coloured-through finish so no painting. At the typicals: 95 m² × $63 = $5,985. The acrylic row ($46–$80/m²) sits above cement ($34–$69/m²), and the fiddly junction detailing where new meets old is what moves a Hebel job up within it.

4. Painted-brick semi, acrylic over bonding primer

140 m² of previously painted brick — the expensive trap. Paint can't be rendered over with cement, so an acrylic system with bonding primer is used, plus crack repair on the party wall. At the typicals: 140 m² × $63 = $8,820, plus crack repair at $57–$115/m² of the area patched. Tight terrace access that moves all material and waste through the house is what pushes a job like this toward the top of its rows; the acrylic system is the premium over a bare-brick job of the same size.

5. Besser block granny flat, cement render and paint

96 m² of new besser block, bonding coat plus two-coat cement render and a sand texture finish, painted. At the typicals: 96 m² × $52 = $4,992, plus 96 m² × $23 painting = $2,208 — $7,200 all up. Flat block keeps material down and ground-level access keeps it simple, which is what holds a block job toward the bottom of the cement row.

6. Feature wall only, texture coat

One 24 m² street-facing wall, a fine texture-coat render system in a coloured-through finish to match a renovation. At the typicals: 24 m² × $80 = $1,920 (the row is $57–$115/m²). Small areas carry fixed set-up and minimum-day charges on top of the per-metre rate, so ask how a renderer prices a single wall. Worth it to many owners for the kerb appeal.

7. Whole double-brick home, two-storey cement render and paint

300 m² of solid double brick, two-storey, two-coat cement render with a wood-float finish and full repaint. At the typicals: 300 m² × $52 = $15,600, plus 300 m² × $23 painting = $6,900, plus two-storey scaffolding at $2,875 — $25,375 before any crack-cutting and patching ($57–$115/m² of repaired area). For comparison, the table's two storey house (approx 300 m²) row is $13,800–$43,700. A big, straightforward masonry job.

8. Mixed-substrate renovation, cement below and acrylic above

Brick ground floor (cement render) and sheet-clad upper storey (acrylic render), 230 m² in total, matched at the finish so the house reads as one. Splitting the area evenly for the working — 115 m² each way — at the typicals: 115 m² × $52 cement = $5,980, 115 m² × $63 acrylic = $7,245, 115 m² × $23 painting on the cement half = $2,645, plus two-storey scaffolding at $2,875 — $18,745 all up. Two systems on one home, scaffolding, and the coordination to blend them is a common Sydney reno scenario and a clear example of why mixed substrates lift a quote.

What the numbers tell you

Three patterns run through every example above. First, substrate sets the system and the system sets the rate — Hebel and painted brick force acrylic ($46–$80/m² in our Sydney table) and cost more; bare brick and block allow cement ($34–$69/m²). Second, height is the reliable multiplier: every two-storey job carries scaffolding — $1,725–$4,600 in the table — before a trowel moves. Third, the table prices per square metre, but a small job carries fixed set-up and minimum charges on top, so a single feature wall costs more per metre than a whole house. When you read your own quotes, find the per-m² rate, then check it against the substrate, the height and the finish before you compare one against another.

Step 1 of 2

What do you need a callback about?

One tap — we'll show you the going rate, then take your number.

You're in.

A local installer will be in touch about your job. No spam, no call centre.

Frequently asked questions

What does it cost to render a whole house in Sydney? Our Sydney table has a whole house exterior (approx 200 m²) at $12,050–$27,600, a single storey house (approx 150 m²) at $9,200–$20,700 and a two storey house (approx 300 m²) at $13,800–$43,700 — single-storey bare brick at the low end, two-storey with premium finish or mixed substrates at the high end.

Why does a small feature wall cost more per square metre? Fixed set-up, travel and minimum-day charges spread across just 24 m². Small areas always carry the highest effective rate, whatever the per-m² row says.

How much of a two-storey quote is scaffolding? Two-storey scaffolding is $1,725–$4,600 in our Sydney table, typically $2,875 — the main reason a double-storey render costs far more than twice a single-storey one of the same footprint.

Should I get more than one quote? Always. Make sure each names the render system, coat count, prep included and whether painting is in or out, or you'll be comparing numbers that aren't measuring the same job.

← Back to Sydney rendering cost hub

Advertise with us

Reach thousands of Australian homeowners researching trade costs. Fill in your details and we'll be in touch within 1 business day.

Thanks! We'll be in touch

Expect a reply within 1 business day.

Got a question about costs?
Chat with Sam
Sam the Platypus
Online now
Powered by What's The Damage
Call Sam 02 9538 7348 Call